Huntsville Utilities

contractors

Water High Level Fees

Effective September 26, 1986

Any service line that is tapped on a main served by one of the following reservoirs requires a $482 high-level fee per lot/unit in addition to the regular tapping fee.

Big Cove
Garth Mountain
East Governors Dr.
Monte Sano
72 East
Smithers Mountain
Toll Gate
Weatherly Mountain

Any service line that is tapped on a main served by one of the following reservoirs requires a $964 high-level fee per lot/unit in addition to the regular tapping fee.

Inspiration Point
Russell Hill II
Green Mountain (mains installed by developer)
Huntsville Hills
Mathis Mountain
Hampton Cove Tank

Any 1″ service line that is tapped onto an existing water main on Green Mountain requires a $2,589 tapping fee per lot/unit.

Dig Safely

Stay Connected

Facebook Twitter